Sachet Line
A sachet line is sold on speed and price, but the numbers that decide total cost are utilities and floor space. I have budgeted a 18,000 sachets/hr sugar line in Cairo where compressed air and power were 14% of operating cost and the footprint forced a second shift. If the quotation omits utilities and footprint, it has not priced the line.

Sachet Line
"Sachet line" is rarely one machine. A complete line is a vertical form-fill-seal or multi-lane unit, a product feeder, a printer for lot codes, a checkweigher, a metal detector, a cartoner or collar, and a case packer — plus the air, power, and water that run them. The quotation that prices only the former and sealer has priced a third of the cost. Read the scope before you read the speed.
| Station | What it costs (relative) | Often omitted |
|---|---|---|
| VFFS / multi-lane former | 1.0 | Spare forming collars |
| Product feeder | 0.3 | Agitation for cohesive product |
| Printer + checkweigher + metal detector | 0.4 | Reject confirmation |
| Cartoner / case packer | 0.6 | Format change parts |
| Utilities + integration | 0.3–0.5 | Air compressor, wiring, layout |
Compressed air is the silent cost. A multi-lane sachet line at 18,000/hr draws 600–900 NL/min at 6 bar; the compressor and its power are yours, not the vendor's. Sealing bars draw 8–15 kW; the printer and checkweigher add more. Water matters only if you clean in place, but most sachet lines are dry and clean by access, not CIP. Budget utilities as a line item, or the operating cost surprises you.
| Utility | At 18,000 sach/h | Annual cost indicator |
|---|---|---|
| Compressed air | 600–900 NL/min @ 6 bar | Compressor power + service |
| Electrical | 12–18 kW | ~ 14% of operating cost |
| Water | Minimal (dry line) | Negligible |
A turnkey line is 8–14 m long and needs 2.5–3 m of service aisle on each side. In a cramped hall, that footprint forces a single shift and caps volume; in Cairo we laid the line in an L to fit the hall, which added a transfer but avoided a second-shift lease. The footprint is a capacity decision, not a drawing detail. Confirm the layout against your actual wall positions before signing.
The gap between "machine delivered" and "line running" is integration: conveyors between stations, electrical panels, PLC handshake, and commissioning. Budget 15–30% of the machine price for this, or the line sits in crates. Require the vendor to quote integration as a line item with a commissioning date, not as "included" in a vague sentence.
The plant specified a 18,000 sachets/hr sugar line (4 g, 8-lane) for hotel and foodservice. The initial quotation covered only the former and sealer at a low price; utilities, cartoner, and integration were separate. We built the full scope: 8-lane VFFS, auger feeder with agitation, inkjet printer, checkweigher with reject confirmation, cartoner, and a 700 NL/min compressor.
Measured utilities were 15 kW electrical and 700 NL/min air — about 14% of operating cost. The L-layout fit the 11 m available hall without a second shift. Total installed cost ran 38% above the "machine only" quote, but the line started on the committed date and hit 18,000/hr in week two.
| Parameter | Machine-only quote | Full-scope build |
|---|---|---|
| Price basis | Former + sealer | Turnkey line |
| Utilities (elec / air) | Not stated | 15 kW / 700 NL/min |
| Utilities share of OpEx | Unknown | ~ 14% |
| Integration | Vague | Itemised, dated |
| Start to 18,000/hr | Uncertain | Week 2 |
CE marking; food contact under EU 10/2011. For sugar, average quantity rules apply. Lot-code printing supports traceability expected under food law.
FDA 21 CFR 110 for food contact; NIST Handbook 133 for net quantity. No EU-style average-weight rule, but lot coding is expected.
Egypt bridges Africa and the Gulf; for broader SEA (Thailand, Vietnam, Indonesia), halal covers the Muslim market. High ambient heat raises compressor load — size the air supply for summer.
Saudi SFDA and GCC anchor conformity; halal (SASO/GSO) mandatory. Summer heat pushes utilities up; budget compressor capacity for 45 °C ambient.
Because the quote covered the former and sealer only. Feeder, printer, checkweigher, cartoner, and integration are the rest. Always price the line, not the machine.
At 18,000 sach/h, about 700 NL/min air at 6 bar and 15 kW. That is ~14% of operating cost. Size the compressor for summer ambient or it stalls.
A line is 8–14 m long with service aisles. Confirm the layout against real walls; a bad fit caps you at one shift. In Cairo, an L-layout avoided a second-shift lease.
Between 15 and 30% of machine price, and it is the gap between crates and a running line. Require it itemised with a date, or it slips.
Written by Helen Xu | Chief Industrial Application Engineer
Helen Xu is a Chief Industrial Application Engineer with 9 years of specialized experience in packaging machinery and liquid filling machine design, equipment model selection, and full production line process optimization. He focuses on delivering customized packaging & filling solutions for pharmaceutical, food, and chemical manufacturing industries, with mature practical expertise in GMP compliance, ISO 9001 quality management standards, and turnkey large-scale filling & packaging production line integration.